The Doha Metro project is closer to its target : 90% Done!
- 7 years ago
"2018 continues to be filled with success! The Doha Metro project is closer to its target, ahead of time, by exceeding 90% complete as of September 2018. See our latest progress overview".
Overall Metro Phase 1 and Lusail Tram progress exceeds 90%
The final stages of testing and commissioning for the first section of the Doha Metro Phase 1 (the System Demonstration) commenced on time – with trains running beneath Doha in fully automatic mode and at full line speed;
5 stations handed over to the Operator RKH - Economic Zone, Ras Bu Fontas, Al Wakra, Al Doha Al Jadeda, Oqba Ibn Nafie
QCDD inspections completed at 5 stations, in progress at all remaining stations
(PSD) Platform Screen Doors and Automatic Fare Collection (AFC) gates installation are 100% complete
Systems integrated testing progress 50% complete
Depot Red Line South: Physical works are 100% complete at all depot buildings, QCD certificates given to 15 buildings
Station Area Works on-going at all stations
53 trains have been delivered to date, 15 of which are fully tested, dedicated to section 1 and ready for operations
The Service Provider has moved into a number of stations and parts of the depot and stabling yard – and other operational readiness activities are also well progressed.
About Qatar Rail:
Website: https://www.qr.com.qa/English/Pages/default.aspx
Facebook: https://www.facebook.com/qrc.official
Instagram: https://www.instagram.com/qrc_official/
Twitter: https://twitter.com/qrc_official
Comments